Section 23
Settlement of the contract in case of death of the contractor before payment of the contract period or if the contractor breaks or abandons the contract

(1) If a contractor who has received a government contract dies before the period of the contract has been paid, the contract settlement shall be made within thirty days by stating that the person entitled or entitled to the contract will take over the contract. If an application is made before the station, office or officer, the contract will be given to such applicant for the remaining period subject to this Act and the rules made under this Act. If both persons apply, priority will be given to the beneficiary. (3) If a contractor abandons or breaks the contract without paying the contract period, the contract will be given to him if the person who is the contractor's guarantor agrees to take the contract under the same conditions as before and submits the application within thirty-five days.< /p>

(4) In the event that someone else receives the contract in accordance with sub-section (1) or (3) or in accordance with sub-section (5), the former contractor or his successor shall not have any rights or obligations in relation to the work related to the contract after that date.

(5) If any person who is eligible to receive a contract under sub-section (1), (2) or (3) does not submit an application to receive the contract accordingly, another contractor for the remaining period subject to this Act or the rules made under this Act. It can be arranged.